BLND4LS LV Large Storage / Hybrid tariff guide
Who this is for
New low-voltage storage or generation connections above 250 kW with no co-located load.
How the bill works
This tariff is for a separate battery or hybrid connection. It is not for a normal business load.
What solar changes
Do not use this tariff to assess solar that shares a meter with normal business equipment.
What a battery changes
Treat this as a specialist connection project. The connection design and market contract control the result.
Check before you model
- Confirm this code on a current retailer bill.
- Check the connection approval, export limit and protection design.
2026–27 network schedule
The price signal behind this code
Network rates only. These are not retail electricity prices.
Published network rates
- Access
- $22.3346/day
- Peak import demand
- $15.1181/kVA/month
- Shoulder import demand
- $13.2946/kVA/month
- Off-peak import demand
- $4.4127/kVA/month
- Evening export rebate
- -5.1906 c/kWh · 5pm–8pm
- Daytime export charge above 1.5 kW
- $1.195/kW/month · 10am–3pm
When it applies
Import demand uses the storage time bands. Daytime export charges apply from 10am to 3pm. The LV evening rebate applies from 5pm to 8pm.
Illustrative exampleClassify a 300 kW LV storage project
- The new battery connects at low voltage.
- Its rated power is 300 kW.
- Only ancillary load shares the meter.
The published tariff path is BLND4LS because the LV storage rating is more than 250 kW.A normal behind-the-meter battery does not use this path. Confirm the connection design with Essential Energy.
Battery opportunity lens
Tariff screen—not a savings quote
Specialist fit
Dedicated storage dispatch
This code is designed for a storage or hybrid connection, not proof that a battery suits an ordinary business load behind the existing meter.
What dispatch can affect
- Time-varying storage import or export components published for the dedicated connection.
- Market or retailer value where the connection and operating agreement allow it.
What it cannot erase
- The bill of a separate business load that is not connected behind this meter.
- Connection, protection, augmentation and market-access costs.
Evidence required
- Connection application, export envelope and network study.
- Half-hourly import and export dispatch model.
- Retailer, market-access and aggregation terms.
- Battery degradation, availability and round-trip efficiency assumptions.