BLND4SBLV Small Scale Storage

Essential Energy · Available · Low voltage · 2026–27

Regional, rural and remote NSW, including most areas outside the major coastal networks.

BLND4SB LV Small Scale Storage tariff guide

Who this is for

New low-voltage storage-only connections up to and including 250 kW.

How the bill works

This tariff is for a separate battery or hybrid connection. It is not for a normal business load.

What solar changes

Do not use this tariff to assess solar that shares a meter with normal business equipment.

What a battery changes

Treat this as a specialist connection project. The connection design and market contract control the result.

Check before you model

  • Confirm this code on a current retailer bill.
  • Check the connection approval, export limit and protection design.
2026–27 network schedule

The price signal behind this code

Network rates only. These are not retail electricity prices.

Published network rates

Access
$2.3784/day
Peak import demand
$15.4927/kVA/month
Shoulder import demand
$6.8171/kVA/month
Off-peak import demand
$4.9726/kVA/month
Evening export rebate
-5.1906 c/kWh · 5pm–8pm
Daytime export charge above 1.5 kW
$1.195/kW/month · 10am–3pm

When it applies

Import demand uses the storage time bands. Daytime export charges apply from 10am to 3pm. The LV evening rebate applies from 5pm to 8pm.

Illustrative example

Classify a 200 kW LV standalone battery

  • The new battery connects at low voltage.
  • Its rated power is 200 kW.
  • No business load or generator shares the meter.
The published tariff path is BLND4SB because the battery is storage-only, low voltage and no more than 250 kW.

This classification does not confirm connection approval or project value.

Battery opportunity lens

Tariff screen—not a savings quote

Specialist fit

Dedicated storage dispatch

This code is designed for a storage or hybrid connection, not proof that a battery suits an ordinary business load behind the existing meter.

What dispatch can affect

  • Time-varying storage import or export components published for the dedicated connection.
  • Market or retailer value where the connection and operating agreement allow it.

What it cannot erase

  • The bill of a separate business load that is not connected behind this meter.
  • Connection, protection, augmentation and market-access costs.

Evidence required

  1. Connection application, export envelope and network study.
  2. Half-hourly import and export dispatch model.
  3. Retailer, market-access and aggregation terms.
  4. Battery degradation, availability and round-trip efficiency assumptions.